Difference between revisions of "Logframe in DPP of DAE"

From Blue Gold Program Wiki
 
(No difference)

Latest revision as of 03:46, 9 November 2021

This logframe was prepared in November 2012 and included in DAE's original Development Project Proforma (DPP) which was recast in May 2013. The logframe was revised in April 2018 for the RDPP (approved in October 2018) to extend the project period to end-December 2020 from the original project completion date of end-December 2018.

Narrative Summary Objectively Verifiable Indicators (OVI) Means of Verification Important Assumption
Goal :

To improve livelihood of small-scale farmers in polders of Khulna, Satkhira, Patuakhali & part of Borguna district.


Increase household income of farmers in the project areas by 15-20% after pc.

Households expenditure on housing and education increased up to 20% after pc



Compare Benchmark survey  & Follow up survey,

mid-term evaluation , Project evaluation


No major natural disasters

Political stability

Purpose :

Crop production of the Project area will be increased by intensifying & diversifying.

Increase area under modern cultivation practices up to 20% (field crops, fruits and vegetables) by project period.

Per capita income improved by 10 -12%.

Modern production technology adoption increases by 20% by 2018.

Follow up survey, field survey, Impact assessment report and outcome surveys undertaken by the M&E unit. Farmers willingness to follow modern cultivation practices.

No natural calamities.

Output
  • About 37,300 (1492*100) farm family trained on modern production technology.
  • Planting materials distribution, established demonstrations 380).
  • Skilled manpower (FFS facilitators-75 DT, monitor) in DAE.
  • Developed 150 Farmer Trainer (FT).
  • Supported established Farmers organization
  • Ensured vehicle
  • Induced use of machinery & equipment.
  • Developed ICT facilities.
  • 1492 no. of FFS organized on modern production technology by project period.
  • Distributed 4000 fruit saplings, vegetable seeds, fertilizers with other inputs for 380 demonstrations.
  • Implemented 2 batches TOTs to develop FFS facilitators, 6 batches tag SAAOs, 4 batches of FFS monitor, 25 motivational tours, workshop on technology selection (3), awareness creation (1) & seasonal review & planning (10) by the project period.
  • Provided support of Tk 20,000/ (Tk twenty thousand) to 375 good farmers groups/clubs.
  • Received two Jeeps from the Embassy of Netherlands, Procured 25 motorcycles by 2014.
  • One digital camera, one photocopier, one Fax machine, one Multimedia, one Air Conditioner, one IPS procured by 2014.
  • Two Laptops & two desktop computer procured by 2014
  • Participatory monitoring feedback and surveys.
  • Project reports
  • Progress report
  • IMED report
  • Production statistics.
  • Project personnel will not be over burdened with additional charges.
  • Availability of sweet  water will ensured in time.
  • No natural hazard/ Calamity and political unrest.
  • Co-operation from other related Ministries, departments, agencies and farmer groups.
  • GoN allocation will be available in time
  • Timely availability of quality inputs.
Inputs/Activities
  • Man power with additional charges
  • Providing Training of GoB staff on FFS
  • Distribution of planting materials,  Seeds, FYM  with other inputs for demonstration with field days
  • Training of FFS Facilitators
  • Training of FFS monitor
  • Training of Tag SAAO
  • Implementation of  FFS
  • Implementation of FFS representation/ motivation tour.
  • Support to Farmers Organizations (FO)
  • Motorcycle with other capital components  procured.
  • Transport facilities
  • 3 number of manpower to be ordered for additional charges by January 2013.
  • GoB Staff trained by 2018 -11 lakh taka
  • 4000 planting materials, different kinds of seeds, FYM with other inputs to be distributed to establish 380 demonstrations by 2018   -81.60 lakh taka
  • 2 batches of FFS facilitator trained by 2015. - 91.80 lakh taka
  • 4 batches of FFS monitor trained by 2016 - 6.00 lakh taka
  • 6 batches of Tag SAAO trained by 2016 - 4.80 lakh taka.
  • 1492 FFS implemented by 2018. - 612 lakh taka
  • 25 batches of FFS representation /motivational tour implemented by 2018.-12.50 lakh taka.
  • Completed support to 375 Farmers Organization/club by 2018- 75.00 lakh taka.
  • Procured 25 motorcycles,4 computers set,1 photocopier and furniture procured by - 2014. - 46.80 lakh taka
  • Receive two vehicles with driver from the Embassy of Netherlands
  • Approved DPP,
  • Project management records
  • Office file
  • Tender document
  • Project reports
  • Timely approved  from Planning Commission,
  • timely set-up of manpower,
  • & GoN allocation .
  • Implementation of activities as par schedule
  • Fund Flow available according to demand.